Work out net present value and the internal rate of return
The idea
Net present value discounts every cash flow of a project at the required return and subtracts the outlay, so a positive NPV means the project adds value at that required return. The internal rate of return is the discount rate that sets NPV to zero, which answers a different question: not how much value, but at what rate. The two agree on accept-or-reject for a single conventional project and can disagree on ranking two, because IRR is only a good proxy for the realised compound return if interim cash flows can be reinvested at the IRR itself, which is a limitation when they cannot. When they conflict, follow NPV - it is the preferred value-maximising criterion and is denominated in money, which is what shareholders actually receive.
Formulas
Net present value
NPV = Σ CFₜ ÷ (1 + r)ᵗ
- CFₜ
- the cash flow at time t, with the initial outlay as a negative CF₀
- r
- the required rate of return
- t
- the period, counted from 0
Accept if NPV is positive. Where NPV and IRR disagree on mutually exclusive projects, NPV wins.
A practice question
Net present value is the present value of a project's future cash flows minus:
- the initial investment - correct
- the discount rate appliedWhy not: A rate cannot be subtracted from an amount of money. The rate does its work inside the discounting, before anything is netted off.
- its internal rate of returnWhy not: Also a rate, so it cannot be subtracted from an amount of money. IRR is a separate measure: the discount rate that sets NPV to zero.
NPV (net present value) tells you how much value a project adds in today's money. NPV = (present value of all future cash flows) - (initial investment). 'Present value' means a future amount shrunk back to today's value. For example, if future inflows are worth 1,100 today and the project costs 1,000, then NPV = 1,100 - 1,000 = 100. A positive NPV means the project adds value.
A harder one
A project costs $1,000 today and pays $1,210 in two years. At a 10% required return, its NPV is closest to:
- $210Why not: The undiscounted surplus, 1,210 - 1,000. It ignores that the $210 arrives only after two years of waiting at a 10% required return.
- $100Why not: This is one year of 10% interest on the $1,000 outlay. It is not a present value: the $1,210 arrives in two years, and discounted by 1.10² it is worth exactly $1,000.
- $0 - correct
Discount the future cash back to today by dividing by (1 + r)^n, then subtract the cost. NPV = 1,210 / (1 + 0.10)² - 1,000 = 1,210 / 1.21 - 1,000 = 1,000 - 1,000 = 0. The project only just breaks even at 10%. This also means 10% is its IRR, the rate that makes NPV zero.
The hardest tier
A project costs $500 now and pays $200 at the end of each of the next three years. At an 8% required return, its NPV is closest to:
- $100Why not: 600 - 500, the undiscounted surplus. Discounting the three inflows takes the total from 600 to 515.42.
- -$15Why not: The right magnitude with the sign reversed. The discounted inflows come to 515.42, which is above the 500 outlay, not below it.
- $15 - correct
Discount each inflow back to today with PV = Cash flow / (1 + r)^t, then subtract the cost. Year 1: 200 / 1.08 = 185.19. Year 2: 200 / 1.08² = 171.47. Year 3: 200 / 1.08³ = 158.77. Total = 515.42. NPV = 515.42 - 500 = 15.42, about +15. The undiscounted total of 600 overstates value because later money is worth less.
In the app: 18 practice questions on this outcome, a narrated walkthrough with diagrams, spaced review that brings it back before you forget it.
Take the free diagnostic →More in The Time Value of Money in Finance
- Work out what a cash flow will be worth in future
- Work out what one cash flow is worth today
- Work out what an annuity and a perpetuity are worth today
- Contrast a stated annual rate with the effective annual rate
- Work out, from market prices, the return implied by a bond and the growth rate implied by a stock
- Explain cash flow additivity and apply it to derive an implied forward rate